Schedule PWD: Timeline for Constructing a Retaining Wall at Pump Bay, Sandy Point By: James Morris Date: July 23, 2024 Share post: FacebookTwitterPinterestWhatsApp Activity – July 25 & 26 – Casting of concrete flooring. July 29 – August 7 – Laying of blocks. August 8 & 9 – Backfilling and cleanup. Time & Location – July 15, 2024 (9:00 am) – August 9, 2024 (3:00 pm) Pump Bay, Sandy Point Previous articleProperty Condition Survey for East and West Shadwell to Begin June 29, 2024Next articlePWD: Timeline for Demolishing and Casting Concrete Drains in Lower Monkey Hill Latest Articles Ministry of Public Infrastructure et al. Expresses Appreciation to Hard-working Staff Shivanna Stevens - February 3, 2025 WSD : Notice for Molineux, Phillips’ and Bourryeau Interruptions Notice of Office Closure on January 30th, 2025 Office Closures Related articles Schedule PWD: Timeline for Clearing Debris and Bush at the South East Peninsula Activity -The team will be clearing the road of debris and overhanging bushes. Drivers are asked to exercise... Public Works Department Daily Tracker for PWD’s Asphalt Crew Nature of Work:The asphalt crew will be cleaning storm drains.When & Where:July 23, 2024 (9:00 am) - July... Schedule PWD: Timeline for Demolishing and Casting Concrete Drains in Lower Monkey Hill Activity -The crew completed the right side of the drain prior. They will focus on the left side.Time...